Estimate
Task | Hours |
---|---|
Study, Scoping and Estimate | 4 |
Deploy token on Base | 5 |
Deploy safe on Base | 1 |
Add UMA oSnap plugin to Snapshot | 2 |
List token on the Base bridge | 2 |
Bridge from L1 to L2 | 6 |
Bridge from L2 to L1 | 6 |
oSnap setup | 4 |
Snapshot tx test | 4 |
(PM) Organization, Context and Management | 6 |
Total: 40h
Cost
Blockful standard rate for Shutter DAO is of $85/h as per our previously approved proposal
$85 x 40h = $3,400
Timeline
The project will be executed inside a period of 2 weeks, from Jan 13th to Jan 27th. We are confident on the possibility of finishing earlier, but this period would allow to accomodate any unexpected changes as seen in the previous work.
Payment
Regarding the payment, Blockful is working on a new proposal to change our process of charging the DAO.
We’ve been discussing with other DAO members that we’ve been finding it hard to balance management work vs execution work due to the standard of small proposals that run separetely, need previous scoping and estimation, proposal writing, reporting and charging every time, spread across time with no regular flow of demands.
We’re big fans of shutter and want to continue our work with 0x36, and for that are working on a proposal to streamline our contributions with a bigger proportion of hours focused at shipping things that benefit the DAO and it’s members.
The new proposal should be on the forum in the next few days. If approved, we’d like to include this payment already through the new process. If the new process is not approved, this proposal should be charged by an end of the month report as previously agreed.